3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days
Alright, lets get started.
The length of each section what carpenter needs to cut is 3 feet and 8 inches.
Converting 3 feet and 8 inches into feet only, we know, 
So, 3 feet 8 inches =
feet
It means length of each section =
feet
Carpenter needs to cut 4 sections, so length of 4 sections will be = 
2/3 feet means 8 inches so she needs board 14 feet 8 inches
Board is only sold by the feet only so, she has to puchase 15 feet board. : Answer
Hope it will help :)
Answer:
15 kilometres
Step-by-step explanation:
Based on the wording of your question, I am assuming you already know that Paul ran 250 metres every 1 minute, and that the ratio is 250:1. To get the second part of the answer, convert metres to kilometres. 0.001*250= 0.25. Paul ran 0.25 kilometres per minute. The ratio of kilometres per minute is 0.25:1. Next, convert minutes to hours. Multiply the entire ratio by 60, as there are 60 minutes in an hour. The ratio of kilometeres per minute is 15:60, and the ratio of kilometres per hour is 15:1, meaning Paul ran 15 kilometres in one hour.