Answer:
NPV = $20,040.35
Explanation
The net present value NPV) of a project is the present value of cash inflow less the present value of cash outflow of the project.
NPV = PV of cash inflow - PV of cash outflow
We can set out the cash flows of the project using the table below:
Annual net cash inflow = Savings - Technician cost = 61,427- 20,000
= $41,427
PV of Cash flow= $41,427 × (1-(1.12^(-5))/0.12= 149,335.06
PV of salvage value = 1.12^(-5)×$6,641 = 3768.281749
NPV = 149,335.06 + 3,768.281 -133,063= 20,040.35
Answer:
Budgeted overhead= $283,400
Explanation:
Giving the following information:
Production:
October= 192,000
variable overhead is applied at a rate of $0.70 per unit of production.
Fixed overhead equals $149,000 per month.
To calculate the budgeted overhead, we need to determine the total variable overhead for the month:
Budgeted overhead= fixed overhead + total variable overhead
Budgeted overhead= 149,000 + 0.7*192,000
Budgeted overhead= $283,400
Answer and Explanation:
The computation of the outstanding checks is shown below:
For the November end
= Checks - presented in the bank
= $10,230 - $8,240
= $1,990
For the December end
= Checks - presented in the bank + presented in th bank - checks
= $10,230 - $8,240 + $11,815 - $10,655
= $3,150
We simply applied the above formula
Answer:
Debit Accounts Receivable, $225; credit Fees Earned, $225
Have a fantastic Day!