Answer: B, Amerigo could work with school administrators, the principal, and private tutors to find the time, money, and classroom space for tutors to give after-school Italian lessons.
Explanation:
Edge 2020.
Answer:
i AM SORRY BUT I DONT UNDERSTAND WHAAT YOU ARE TRYING TO SAY TRY TO MAYBE REWORD IT (SORRY FOR THE CAP LOCK)
Explanation:
All are assumed except <u>A. Total variable costs remain the same over the relevant range.</u>
<u />
Cost-volume-profit analysis examines how changes in cost in volume affect income. Variable costs are ones that go up and down depending on production levels, so it would not make sense to assume that variable costs stayed the same over the relevant range.
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.