Coase theorem is a private solution for the two parties who agree to reduce externalities, i.e., pollution. They negotiate in such a manner that the costs are low as one party takes over other party's polluted assets to reduce pollution. When there are more parties or firms involved to eliminate pollution, it will pose high transaction costs. Therefore, the Coase theorem will not work in that case. So, the option "D" is the correct choice.
<span>The stage of the consumer decision making process that is represented is needing recognition. When Sam's car was totaled by someone hitting a stop sign, Sam found out his car could not be repaired therefor he discovered that he needed a new car. This was recognizing the need, which was to replace his vehicle.</span>
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.