Answer:
Explained below.
Explanation:
There are some of the difficulties in measuring innate capacity and in measuring developed performance are as follows:
* Primarily we do not know precisely what innate abilities are or how to measure them so it is one of the difficulty while measuring innate capacities.
* And with the measurement of performance abilities, there is no single, all-inclusive performance criterion.
Answer:
True
Explanation:
Critical-Chain
This was introduced or originated by Eli Goldratt in 1997. Its aim is to challenges conventional project management approaches and absolute dependence on TOC principles. The idea of what to change or eliminated is the largely rooted behaviors that is common with the traditional project management practices. It is very multitasking anf it is the longest string of reliance that occur on the project.
Critical- Chain Approach
This approach simply covers project network as it ca be limited by both resource and technical reliance/dependencies. each type of limitations can create task reliance.
The Summary of Critical Chain Approach
1.) use Aggressive but Possible Times (ABPT) for task durations
2.) identify the critical chain by accounting for resource dependencies
3.) use buffer management to track project progress etc.
Answer:
C) By lowering the price of the flower arrangements to increase demand.
Explanation:
According to the law of demand, the lower the prices, the higher the quantity demanded and the higher the price ,the lower the quantity demanded.
When prices are reduced, demand increases, revenue increases and net profit increases.
I hope my answer helps you.
It is called the Naegele's run the show. It predicts an expected due date in light of the beginning of the lady's last menstrual period. You just extra nine months and seven days to land at the due date.
It is a standard method for ascertaining the due date for a pregnancy while expecting a gestational age of 280 days at labor.