Answer:
A. Pure project A project manager leads personnel from different functional areas = Team members can work on several projects. Duplication of resources is minimized.
B. Functional project Personnel work on a dedicated project team = Team pride, motivation, and commitment are high.
C. Matrix project A team member reports to two bosses = The project is housed within a functional division of the firm.
Explanation:
For A answer, this kind of project management conducts the people, to work on a multitasking way, because they have to accomplish the responsibilities on their functional area as the same that they must accomplished their responsibilities on the project areas. This can minimized the resources for the project but could impact negatively on the compliment of responsibilities because is the same person for two work fronts.
For B answer, if the people can focus their efforts only in the project, that creates more interest on reach the goals efficiently than if the team were distributed on functional and projects departments
For C answer, when the project is developed in a functional division of the firm, you, as a team project member, must report to the project manager and your functional area boss.
Business Financial Management
Answer:
c.
Explanation:
the product is a "me-too" and contains no new technology or points of difference
Price skimming is a pricing strategy in which a marketer sets a relatively high initial price for a product or service at first, then lowers the price over time
Answer:
Allocated MOH= $4,000
Explanation:
Giving the following information:
Machine hours used 1,000 hours
If total manufacturing overhead costs during the month totaled $100,000 when a total of 25,000 machine hours were used
First, we need to calculate the estimated overhead rate:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 100,000/25,000= $4 per machine hour
Now, we can allocate overhead to Product 95:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 4*1,000= $4,000
self-interest. Focus on actions or activities that are advantageous to an individual or organization. For a business or individual to survive and grow, a degree of self-interest is necessary.