Answer:
$370.69
Explanation:
Given the following :
Capacity (n) = 430
Cost incurred by airline per flight = $4000 + $60 per passengers
If ticket price = T ; (430 - 0.58T) are expected to book.
Determine the ticket price, T, that will maximize the airline's profit.
Profit = Revenue earned - cost incurred
Revenue earned = capacity * price = nT
Cost incurred = $4000 + $60n
Profit = nT - (4000 + 60n)
If ticket price = T ; (430 - 0.58T) are expected to book. Then n = (430 - 0.58T)
Profit = (430 - 0.58T)T - ($4000 + 60(430 - 0.58T))
Profit = 430T - 0.58T^2 - ($4000 + 25800 - 34.8)
Profit = 430T - 0.58T^2 - 4000 - 25800 + 34.8
Profit (P) = - 0.58T^2 + 430T −29834.8
Taking the first derivative of P
P' = 2(-0.58T) + 430
P' = - 1.16T + 430
Hence solve for price (T) when P' = 0
0 = - 1.16T + 430
1.16T = 430
T = 430 / 1.16
T = 370.68965
Price = $370.69
Finishing this job could cost as low as $222,000 in total. If the project is finished in 45 weeks, the final cost will be $400,000. If the project is completed in 46 weeks, the overall cost will be $405,000. The project is finished in 45 weeks, which has the lowest overall cost.
This project can be finished for as little as $222,000 overall. This is so that there is no penalty if the project is finished in 45 weeks. A $5,000 fine is imposed if the project is finished in less than 46 weeks. Thus, completing the project in 45 weeks results in the lowest overall cost. Examining the costs associated with each action is one method to approach this. The first activity will cost $40,000 to complete. The second activity will cost $60,000 to complete. The third activity will set you back $80,000. The fourth action will set you back $100,000. The sixth activity will set you back $120,000. The project will cost $400,000 in total. The overall cost, if the project takes 45 weeks to complete, is $400,000. The whole expense is $405,000 if the project is finished in 46 weeks. Thus, completing the project in 45 weeks results in the lowest overall cost.
To know more about Cost, refer to this link:
brainly.com/question/20534030
#SPJ4
Answer:
Please see the answer below:
Explanation:
(a)
Debit: Accumulated Depreciation $53,990
Credit: Delivery Equipment $53,990
To record disposal of delivery equipment.
(b)
Debit: Accumulated Depreciation $37,080
Debit: Loss $16,910
Credit: Delivery Equipment $53,990
To record Loss on disposal of Delivery Equipment.
Answer:
a.- $ 3,529.82
b.- $ 3,512.11
c.- $ 132,77
Explanation:
In each case, we must calculate the value of their current savings and the additional investment.
The saving are the same for each scenario so let's calculate that first:
Principal 1,500.00
time 15 years
rate 0.01000
Amount 1,741.45
Then we add the funds generated from the investment:
a.- 110 annuity due for 15 month:
C $ 110
time 15 months
rate 0.01
FV $1,788.3651
We add the savings and get a total of: $ 3,529.82
b.- 110 ordinary annuity
C $ 110
time 15 months
rate 0.01
FV $1,770.6585
Plus, original savings of 1,741.45 = 3,512.11
c.-
If they need 3,900 then the fund must cover the difference between these and the savings future value:
3,900 - 1,741.45 = 2,158.55
Now we calculate the PMT, considering the payment are at the beginning:
FV $ 2,158.55
time 15
rate 0.01
C $ 132.770
Answer:
B. Value-conscious.
Explanation:
In the scenario above Preshant can easily be tagged a value-conscious consumer particularly because of her keen interest and concern for price and goods quality.
It is also noted that their have always been segments of the population to whom value has mattered. This is especially the low-income families have long since used tactics such as coupon clipping to get the most out of their spend. However, as the economy recovered and strengthened, this prediction did not materialize.