Answer:
12
Explanation:
Because of the fifty percent of
They all are woody products being made up of wood.
Answer:
$6,788
Explanation:
The computation of the supplies cost in the planning budget is shown below:
= Supplies cost per month + number of frames in planned activity × per frame cost
= $1,640 + 572 frames × $9
= $1,640 + $5,148
= $6,788
We simply added the supplies cost and the planned frame cost so that the supplies cost for the planning budget could come
Answer:
B. $300,000
Explanation:
The computation of the reduction of retained earning amount is shown below:
= Number of shares of common stock × stock dividend percentage × market value
= 1,000,000 shares × 6% × $5
= $300,000
Since the dividend amount is adjusted while computing the ending balance of retained earning balance and the same is to be considered in the computation part.
All other information which is given is not relevant. Hence, ignored it