First you would want to add all like terms. So add -2x and -x which will give you the equation -3x+8=?. Now you want to get 8 on the other side to simplify the equation even more so subtract 8 on both sides. -3x=-8. Finally you want to isolate x by dividing by -3 on both sides which will leave you with x=8/3 or x=2 2/3
Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:
P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,
The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.