Answer:
$48,000
Explanation:
The working capital is the business asset that is used for day to day operation. It can be calculated as follows,
Working capital = Current assets - Current liabilities
So,
Working capital = $396,000 - $348,000 = $48,000
It can be verified with the following equation
Fixed assets + Working Capital = Shareholder Equity + Long term Liabilities
Which is,
Fixed assets + Working Capital = $512,000 + $48,000 = $560,000
Shareholder Equity + Long term Liabilities = $298,000 + $262,000 = $560,000
Hope that helps.
Answer:
4
Explanation:
Data provided in the question
Annual demand of product A = 1,000,000 units
Per week production for one machine = 4,500 units
So for annual the production for one week is
= 4,500 weeks × 52 weeks
= 234,000 units
Now the gap left is
= 1,000,000 units - 234,000 units
= 766,000 units
So, the similar machines would be
= 766,000 units ÷ 234,000 units
= 3.27
= 4 round off
Answer:
The answer is option (c), no he will not pass because he is running 4.8 miles in 35 minutes
Explanation:
This can be expressed as;
Speed=Distance/Time
where;
Distance to be covered=5 kilometers
Time=35 minutes
replacing;
speed=(5/35)=0.143 km/min
In order to pass the fitness test his speed has to be greater than 0.143 km/min
Determine if 3 miles per 35 minutes is greater than 0.143 km/min
I mile=1.6 kilometers
How many kilometers make 3 miles,
Jimmy runs=(3×1.6)=4.8 kilometers in 35 minutes
Speed=4.8/35=0.137 kilometers/minute
Speed jimmy runs (0.137 km/min)<the pace he needs to run to pass fitness test(0.143 km/min)
The answer is option (c), no he will not pass because he is running 4.8 miles in 35 minutes
Answer:
The cash payments for September are $646000
Explanation:
The cash payments for merchandise are divided into to parts. The previous month's 70% payments and this month's 30% payments. Thus, the cash payments for the month of september will be 70% for AAugust purchases and 30% for september's purchases.
Thus the cash payments for merchandise will be,
Cash Payments = 0.7 * 610000 + 0.3 * 730000 = $646000
Answer:
The correct answer is d. planned value
Explanation:
Among project managers, the Earned Value is one of the most demanded requirements of management tools. When we talk about it, we refer to Earned Value Management (EVM), a series of parameters that advise on the operation of the project based on a planning. The Earned Value will inform us of the cost and time deviations of the project. So, thanks to its functionality, we can make faster and more effective decisions, based on concrete data about the reality of the work performed.