Answer:
C, Or D.
Explanation:
<em>Because A speed enhancing hard drive Can store any type of quick file if you just click on it will load fast. Same thing goes for a hard drive but you have to transfer the file</em>
Answer:
3. alpha = {1, 5, 6, 7, 5}
Explanation:
Initially, we have that:
alpha[0] = 1;
alpha[1] = 2;
alpha[2] = 3;
alpha[3] = 4;
alpha[4] = 5;
For j higher than 2, we have that:
alpha[j - 1] = alpha[j] + 2;
So
j = 3
a[2] = alpha[3]+2 = 4 + 2 = 6;
j = 4
a[3] = alpha[4]+2 = 5+2 = 7;
The correct answer is:
3. alpha = {1, 5, 6, 7, 5}
Answer:
Optimistic duration
Explanation:
The following three concepts are Project management concepts:
Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.
Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc
Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.
Which of the following is the estimate of the minimum amount of time it would take to perform a task?
The answer is Optimistic duration
Answer:
in controlling the mouse or cursor
Explanation:
as is it known tha a cursor is a poniting device. and the only way to control it without a mouse is the touchpad