One person hour is a unit indicating the rate at which one person is working on the project .
The company estimates that it will take 2880 person- hours to complete the job
So let's determine how many hours it will take 12 workers to complete same job
The rate = 2880 person/hour
12 persons or workers =( 2880 person/hour)/12 persons
12 persons or workers = 2880/12
12 persons or workers=240 hours
It will take 12 workers 240 person hour to finish the project.