Answer:
The Firm should not Buy and Install the press as it delivers a negative NPV of -$24,924 at 11% discount rate over its 4 year operations
Explanation:
The General rule is to appraise the investment based on various appraisal techniques.
A technique that should be considered must have special focus on the time value of money, the required rate of returns expected by the firm and other Cashflow considerations.
The Net Present Value (NPV) approach will be the best method to proceed with.
The NPV approach typically falls under the following decision tree:
a. If NPV is negative (Reject the proposal)
b. If NPV is positive (Accept if it's a singular project, Accept the highest positive NPV if it's for mutually exclusive Projects)
c. If Zero (this is the breakeven line at which the Project covers all its cost but does not return a profit.) Also referred to as the IRR
Kindly refer to the attached for detailed workings
Answer:
D.$400 over allocated
Explanation:
For computing the over-allocated or under-allocated amount, first, we have to determine the predetermined overhead rate which is shown below:
Predetermined overhead rate = (Total estimated manufacturing overhead) ÷ (estimated direct labor-hours)
= $371,000 ÷ 180,000 hours
= $2.06
Now we have to find the actual overhead which equals to
= Actual direct labor-hours × predetermined overhead rate
= 190,000 hours × $2.06
= $391,400
So, the ending overhead equals to
= Actual manufacturing overhead - actual overhead
= $391,000 - $391,400
= $400 over - applied
Answer:
No his parents aren't exactly right, a college is far more expensive, not only money wise, but also time wise. These programs/bootcamps can get you started in web design, and make sure you pass with a certificate and fully understand the topic, and they only take around a 2 - 5 months.
Answer:
Sell the parts without any processing because the profit is higher ($20,000 vs $15,000)
Explanation:
they have two options:
- option A, sell the parts as they are and make $20,000 in profits (= $120,000 - $100,000).
- option B, further process the parts by spending $75,000 and sell them for $190,000, and make only $15,000 in profits (= $190,000 - $100,000 - $75,000).
The best option is A, to sell the parts without any processing because the profit is higher and they do not have to spend more money.
If Tara bought, sweater $ 52, T-shirt $19, Shoes $68, Jeans $72, Necklace $21, the total would be;
52+19+68+72+21 = 230
But a tax rate of 7% was included,
Thus, 230 × 0.07 = 16.1
Therefore, the total amount is 230+16.1 = 246.1
Hence, the Estimate amount of money that Tara expects to pay is $250