Answer:
This situation means that resources were not being efficiently used.
If society managed to produce 1 more unit of X with the same resources and technology, this means that some resources were idle in the past, which causes inefficiency.
This also means that the combination 3 units of X and 4 units of Y is a point inside the PPF. However, we do not know if the combination 4 units of X and 4 units of Y is a point inside the PPF, or on the PPF, because there could be some other combination that could be even more efficient (for example 5 units of both X and Y with the same resources and technology).
Answer: indemnification
Explanation: The indemnification clause is essentially the other party's obligation to compensate your damages if they do something that hurts you or allows you to be sued by a third party.
Indemnifying and keeping innocent means the same thing — making it whole after a defeat. Usually, but not always, the obligation to indemnify is reconcilable with the contractual obligation to "keep harmless" or "save harmless.
Hence from the above we can conclude that Rangle has right of indemnification.
Answer:
architectural innovation
Explanation:
The scenario is describing the term known as architectural innovation. This refers to the innovation of the specific architecture of any product that changes and/or modifies the way the different components of the machine link or relate to each other, thus allowing it to perform new functions or the same functions but in a much more user-friendly manner. This is what Canon did by changing the architecture of the copying machine so that it was more user-friendly for the end consumer.
The business cycle where the economy is growing faster than usual.
Answer:
total budgeted costs = $141,570
budgeted production = 1,000 units
standard rate = $141,570 / 1,000 = $141.57 per unit
total actual costs = $135,810
actual production = 850 units
actual rate = $135,810 / 850 = $159.78 per unit
- total fixed overhead variance = actual overhead costs - budgeted overhead costs = $135,810 - $141,570 = -$5,760 favorable. The actual overhead expense was lower than budgeted.
- controllable variance = (actual rate - standard rate) x actual units = ($159.78 - $141.57) x 850 units = $15,478.50 unfavorable. The actual overhead rate was higher than the standard rate, that is why the variance is unfavorable (more money was spent than budgeted).
- volume variance = (standard activity - actual activity) x standard rate = (1,000 - 850) x $141.57 = 150 x $141.57 = $21,235.50 unfavorable. Less units where produced than budgeted, that is why the variance is unfavorable.