i got two new xbox one games 3 sweatshirts and a wallet
Answer:
Critical path = A-D-F-H
Duration = 22
Explanation:
Given:
Activity A B C D E F G H
Time 5 3 7 6 7 3 10 8
The objective is to identify the critical path and to find the time needed to complete this project
Solution:
The possible paths are as follows,
A-C-H = 5+7+8 =20
A-D-F-H = 5+6+3+8 =22
A-D-G = 5+6+10 = 21
B-E-G = 3+7+10 = 20
B-E-F-H = 3+7+3+8 = 21
a)
Critical is the path with the longest duration
Critical path =A-D-F-H
The duration is 22
b)
The duration to complete the project is as follows,
Duration = Length of critical path = 22
The next guesses of the clerk should be less of red shells and more of white shells.
<h3><u>Decision about less of white and more red shells</u>:</h3>
Given that,
Red shell [r] costs = $0.75 each.
White shell [w] costs = $0.49 each.
Total of 8 shells = $4.70
The clerk guesses that the $4.96 for 4 red shells and 4 white shells is greater than the actual purchase.
Therefore,
The clerk should make use of less red shells, and more of white shells, because the unit costs of red shell is more than the white shell.
Learn more about equations, refer:
brainly.com/question/2574274
Answer:
PV= $2,749,494
Explanation:
Giving the following information:
Cash flow= $200,000
Number of periods= 25
Interest rate= 5.25%
<u>First, we need to calculate the future value using the following formula:</u>
FV= {A*[(1+i)^n-1]}/i
A= annual cash flow
FV= {200,000* [(1.0525^25) - 1]} / 0.0525
FV= $9,881,102.14
<u>Now, the present value:</u>
PV= FV/(1+i)^n
PV= 9,881,102.14 / (1.0525^25)
PV= $2,749,494
Answer:
22532
Explanation:
For this one you dont look at the w2 form. you have to look at the form you are filling out go up to question number 7 and 8 you will subtract those to answers that was filled in 34732-12200= 22532
sorry for the long explanation I was currently working on this and then I read the problem so many times but I feel slow so hope this helps