Answer:
If two sides of a rectangle add up to 18cm and the area is 80 units squared then the length is 10cm, and the width is 8cm. If you add 10 and 8 together you get 18, and if you multiply those you get 80 units squared.
Explanation:
Answer:
$120 per unit
Explanation:
The computation of minimum acceptable transfer price is shown below:-
If the division of the transferor does not have spare capacity, the minimum transfer price is equal to variable cost per unit and the contribution margin per unit
Minimum transfer price = Variable cost per unit + (Selling price to outside customers - Variable cost per unit)
= $72 + ($120 - $72)
= $72 + $48
= $120 per unit
Therefore for computing the minimum transfer price we simply applied the above formula.
Answer: Eric will report an Interest Income of $1560
Explanation:
Interest Rate (r) = 6%
Marturity Value = 26000
Interest income for this year
Interest income (6 months) = 26000 x (0.06/2) = 780
Interest income for this year = 780 x 2 = 1560
Eric will report an interest income of $1560 this year.
Interest Income in the final year (Maturity year)
Bond Interest Payments are constant each year for up until the Bond Matures. Eric will still earn an interest of $ 1560 in the final year
The process of discovering, evaluating, and controlling risks to an organization's resources and profits is known as risk management.
<h3>
What is Risk management?</h3>
The process of discovering, evaluating, and controlling risks to an organization's resources and profits is known as risk management. These dangers can be caused by a number of things, such as monetary unpredictability, legal responsibilities, technological problems, strategic management blunders, accidents, and natural calamities.
In order to reduce, monitor, and control the likelihood or impact of unpleasant events or to optimize the realization of possibilities, risk management involves the identification, evaluation, and prioritizing of risks. This is followed by the coordinated and efficient use of resources.
By early risk identification, staff members can lessen the possibility and severity of prospective project risks. There will be a plan of action in place in case something does go wrong. Employees can do this to prepare for the unexpected and improve project results.
To learn more about Risk management refer to:
brainly.com/question/4678268
#SPJ4