ok, 10 men take 84 days to complete a job
therefor, each man completes 1/10 of the job in 84 days
each man does 1/840 of the job per 1 day
so, if we had 5 more, or 15 men
15 times 1/840 times xdays=1 job complete
15/840 times xdays=1job
times both sides by 840/15
xdays=840/15
xdays=56
56 days it would take
Answer:
I am not able to answer your question because I am unsure of what to solve for. :/
Step-by-step explanation:
To write this equation, you need use the formula y=mx+b.
m represents the slope and b represents the y intercept.
The y intercept is the point where the line touches the y axis. In this case, the y-intercept is 1.
The slope is just rise over run from one coordinate to another. The slope is 2/-1 which could be simplified as -2. The slope just means that we are going up 2 and left 1 to get to a new coordinate.
The equation is y=-2x+1
Have a good day! :)
The smallest natural number is 1. The largest natural number does not exists because there will always be one even larger. But if you are asking the number of all natural numbers or the size of natural number set then
is your answer.