Answer: $360,050
Explanation:
The total cost of a fixed asset refers to all the cash that was paid to acquire the asset, transport it and then install it.
Cost of the new machinery is therefore = Discounted cost price + Sales tax + Installation charges + Concrete slab
= (270,000 * (1 - 2%)) + 79,750 + 4,800 + 10,900
= 264,600 + 79,750 + 4,800 + 10,900
= $360,050
<em>Cost price was discounted by 2% as per the credit terms of 2/10 which means that there is a discount of 2% if the asset is paid for in 10 days. </em>
Answer:
The correct answer is letter "A": Level 2 - Enhanced Steady-State.
Explanation:
In the enhanced steady-state (L2) of an emergency, only part of the members of the critical response team is requested to verify the credibility of the threat to find out what are the steps needed to be followed under an unfavorable situation. Among their activities, the staff members issue alerts and coordinate with mission partners.
Answer:
the share should sell at $46
Explanation:
We use the CAPM method to know the required return of the capital
risk free 0.04
market rate 0.1
beta(non diversifiable risk) 2
Ke 0.16000 = 16%
Now we calculate with the dividends grow model the intrinsic value of the share:
![\frac{divends}{return-growth} = Intrinsic \: Value](https://tex.z-dn.net/?f=%5Cfrac%7Bdivends%7D%7Breturn-growth%7D%20%3D%20Intrinsic%20%5C%3A%20Value)
![\frac{4.60}{0.16-0.06} = Intrinsic \: Value](https://tex.z-dn.net/?f=%5Cfrac%7B4.60%7D%7B0.16-0.06%7D%20%3D%20Intrinsic%20%5C%3A%20Value)
$4.6/0.1 = $46
Answer:
Cost of units completed = $176,528
Workings are attached:
Explanation:
Equivalent unit of production
An equivalent unit of production is an expression of the amount of work done by a manufacturer on units of output that are partially completed at the end of an accounting period. Basically the fully completed units and the partially completed units are expressed in terms of fully completed units.
Equivalent units are used in the production cost reports for the producing departments of manufacturers using a process costing system. Cost accounting textbooks are likely to present the cost calculations per equivalent unit of production under two cost flow assumptions: weighted-average and FIFO.
Conversion costs
Conversion costs is a term used in cost accounting that represents the combination of direct labor costs and manufacturing overhead costs. In other words, conversion costs are a manufacturer's product or production costs other than the cost of a product's direct materials.
Expressed another way, conversion costs are the manufacturing or production costs necessary to convert raw materials into products.
The term conversion costs often appears in the calculation of the <u>cost of an</u> <u>equivalent unit in a process costing system.</u>
For the sake of this question, we will be determining the <u>equivalent units of production:</u>
- Units completed and transferred subject to material and conversion costs
- Units in the closing inventory subject to material and conversion costs
- We will then calculate the cost per units with respect to material and conversion costs for the equivalent units.
- These cost per units will enable us to determine the cost of items completed.
Answer:
d. If the WACC is 9%, Project B's NPV will be higher than Project A's.
Explanation:
The internal rate of return is the return in which the NPV is zero i.e cash inflows equal to the initial investment
While the WACC refers to the cost of capital by considering the capital structure i.e cost of equity, cost of preferred stock and cost of debt by taking their weightage
Now if the WACC is 9% so project B NPV would be higher as compared to project A as we can see that project B IRR is greater than the project A IRR
Therefore option d is correct