Answer: 2500
Explanation:
The ending work in progress will be calculated as the addition of the begining work in progress to the units started for the year after which we then deduct the normal spoilage, abnormal spoilage and the units completed from the period. This will be:
= 5000 + 20000 - 22000 - 400 - 100
= 2500
The ending work in progress will be 2500.
Answer:
b. The project's schedule will slip only if the float / slack period for the critical path activities is not enough to resolve the resource overload issue.
Explanation:
This is true because, the resource overload will be an impediment to the critical activities going on in the project. There supposed to be an equilibrium between the resource and the project schedule in-order to ensure completion of the project within the given time frame.
Answer:
B) Land costs; air and rail systems
and
D) Labor cost; proximity to customers
Explanation:
being funny or easy to talk to
Answer:
the quick ratio is 1.4 times
Explanation:
The computation of the quick ratio is given below:
Quick ratio is
= (Cash + Accounts receivables) ÷Current liabilities
= ($120,000 + $80,000) ÷ $140,000
= 1.4 times
hence, the quick ratio is 1.4 times
The same should be considered and relevant