Answer:667
Explanation: un have to added 
 
        
                    
             
        
        
        
Answer:
Answer is the FCAC is greater than the TBC.
Refer below.
Explanation:
A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget. If the cumulative actual cost is greater than the cumulative earned value, then: FCAC is greater than the TBC.
 
        
             
        
        
        
Answer: a. $ 0
Explanation:
The check is only payable if the amount in words and amount in figures matches .In this case since they do not match the check is not payable
 
        
             
        
        
        
Answer:
b. $31,000
Explanation:
The computation of the depreciation expense using the straight-line method for the second year is shown below:
= (Original cost - residual value) ÷ (useful life)  
= ($127,000- $3,000) ÷ (4 years)  
= ($124,000) ÷ (4 years)  
= $31,000
Hence, the correct option is b. $31,000
The units are to be ignored as the method i.e used is straight line so the same is to be considered 
 
        
             
        
        
        
The auditor's count of the client's cash should be coordinated to coincide with the ''count of investment securities'' since both mean counting/managing money.