From the critical path that's given, the total crashing cost will be $530.
<h3>What is a critical path?</h3>
A critical path simply means the longest sequence of tasks that one will have to complete in order to complete a project.
In this case, from the information given, the critical path will be:
= 0 + $130 + $400
= $530
In conclusion, the correct option will be $530.
Learn more about critical path on:
brainly.com/question/10693558
Effective internal communication helps ensure that all members of the organisation are working collaboratively towards a common goal. It develops a cohesive culture and empowers employees to make the right decisions in line with the organisation's goals.
<span>If Bruno's basis in LLC interest is $187,200 he receives $74,880 cash. Bruno's basis in inventory is $51,346 and his basis in land is $64,183. The total value Bruno has in cash, inventory, and land is $190,409. Bruno recognized a gain of $3,209.</span>
Answer:
The answer is stated below:
Explanation:
Note: Here the questions is missing, that is
Which of the following will be a micro economic topic?
Microeconomics is the study which dealt with the knowledge of how the people take decisions at the small scale. It does not consider the economy as a whole.
So, the topic which are related to micr- economic are:
Determine the affects of the war on Iraq on the steel price. This dealt with the affects of war in Iraq, focusing on a single country.
Determine what will happen in the market for the oranges when they are freeze, this also dealt with the market of oranges, not the economy as a whole.
So, both the topics are dealt or related with the micro - economic.