a. $1,420,000
b. $4,514,800
Explanation:
When it comes to fixed assets, all costs that directly helped make the asset available for use are to be capitalized.
Cost of Land
= Purchase Value + Cost Incurred to Tear Down 2 Buildings + Legal Fees + Title Insurance Cost + Assessment Cost - Salvage
= 1,300,000 + 110,000 + 5,000 + 3,500 + 9,500 - 8,000
= $1,420,000
Cost of Building
= Architect's Fees + Liability Insurance Cost + Excavation Cost + Contractor's Payment + Interest Cost
= 46,000 + 3,800 + 15,000 + 4,200,000 + 250,000
= $4,514,800
Answer:
I used an excel spreadsheet since there is not enough room here
Explanation:
Answer:
Expected number of orders=31.6 orders per year
Explanation:
<em>The expected number of orders would be the Annual demand divided by the economic order quantity(EOQ).</em>
<em>The Economic Order Quantity (EOQ) is the order quantity that minimizes the balance of holding cost and ordering cost. At the EOQ, the holding cost is exactly the same as the ordering cost.</em>
It is calculated as follows:
EOQ = (2× Co D)/Ch)^(1/2)
Co- ordering cost Ch - holding cost, D- annual demand
EOQ = (2× 10 × 100000/2)^(1/2)= 3162.27 units
Number of orders = Annual Demand/EOQ
= 100,000/3,162.27= 31.62 orders
Expected number of orders=31.6 orders per year
Answer:
The value of the stock is $28.57
Explanation:
Data provided in the question:
Dividend paid at the end of the year, D1 = $2.00 per share
Increase in dividend = $1.50 per share
Growth rate, g = 5% = 0.05
Required rate of return = 12% = 0.12
Now,
Price with constant Dividend Growth model = D1 ÷ ( r - g )
= $2 ÷ ( 0.12 - 0.05 )
= $28.57
Hence,