Answer:
They would need to buy $64,068.981 in U.S treasury bonds on Ava's second birthday to ultimately provide $120,000 for college expenses in 16 years.
Explanation:
The initial amount to be invested in order to yield $120,000 after 16 years can be expressed as;
F.V=P.V(1+R)^n
where;
F.V=future value of investment
P.V=present value of investment
R=annual interest rate
n=number of years
In our case;
F.V=$120,000
P.V=unknown
R=4%=4/100=0.04
n=16 years
replacing;
120,000=P.V(1+0.04)^(16)
120,000=P.V(1.04)^16
120,000=1.873 P.V
P.V=120,000/1.873
P.V=$64,068.981
They would need to buy $64,068.981 in U.S treasury bonds on Ava's second birthday to ultimately provide $120,000 for college expenses in 16 years.
<h2>Direct to the maintenance department</h2>
Explanation:
Jane here works only in the Maintenance department. The work that he does supports both Production as well as Research. We can calculate the expenses, only by associating the department of the employee.
So, the wages should be directly associated to the maintenance department only.
We cannot add one cost to multiple department and it is not the right approach of accounting system. So the below becomes invalid.
<em>Indirect to the production department Direct to the research department Direct to the production department Indirect to the research department</em>
The term that describes the situation where <em>fixed and variable </em><em>expenses</em><em> are higher than</em> net income is <em>D. dissaving.</em>
Dissaving happens when an individual is spending from either previous savings or borrowing to fund current expenses.
Dissaving is commoner with retirees than those currently employed. But it can also happen to currently-employed persons, whose expenses are more than their incomes. They should find strategies to stop the negative saving. Otherwise, their debts may be overbearing in future.
Thus, dissaving means negative saving or <em>spending more than income.</em>
Learn more: brainly.com/question/13954775
Answer:
a. Project management maturity is an ongoing process based on continuous improvement.
Explanation:
Maturity models are a prospering approach to improving a company's processes and business process management capabilities. It measures the ability of an organization for continuous improvement in a particular discipline.
Project management maturity models are used to: compare practices against an industry standard, define a systematic route for improving project management practices and evaluate current project management practices.
From the above, we can conclude that the maturity models presented in this chapter all demonstrate that Project management maturity is an ongoing process based on continuous improvement.
Answer:
D) Recognized $8.91 million loss on the project in 2022.
Explanation:
The computation is shown below:
For Year 2021:
Percentage of work completed in the year 2021 is
= $40 ÷ ($40 + $84)× 100
= $40 ÷ $124 × 100
= 32.26%
Profit on the contract is
= Contract price - Already incurred cost - Expected cost
= $162 - $40 - $84
= $38
Profit to be recognized in the year 2016 is
= profit × percentage of completion
= $38 × 32.26%
= $12.256
For Year 2022:
Percentage of work completed in the year 2017 is
= ($40 + $65) ÷ ($40 + $65 + $52)
= $105 ÷ $157 × 100
= 66.88%
Profit on the contract is
= Contract price - Already incurred cost - Expected cost
= $162 - $40 - $65 - $52
= $5
Profit that should be recognized till the year 2017 is
= profit × percentage of completion
= $5 × 66.88%
= $3.344
Profit to be recognized in the year 2017 is
= $3.344 - $12.256
= 8.91 million loss