Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.
Points equidistant from DE EF are in the bisector of angle DEF
points equidistant from EF DF are in the bisector of angle EFD
the sought after point is the intersection of bisectricess of triangle
3x-16y-z+9
i know this is right!
hope this helps!