Answer:
2018 loss for 1,500
2019 gain for 4,000
Explanation:
purchase at 715,000
December 31th 713,500
adjusting entry december 31th
loss on investment 1,500 debit
marketable securities 1,500 credit
january 3rd, 2019
cash 717,500 debit
gain on investemnt 4,000 credit
martetable securities 713,500 credit
to record gain on investment
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Answer:
8.14
Explanation:
The Rate of Return is 8.14 from my calculations which you can find in the attached file.
Now since the Rate of return is 8.14. Which is less than MARR of 12%, it shows that investment is not good.