Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.
Answer:
Explanation:IPv4 is almost used up due to the constant increase in devices so therefore IPv6 was implemented to combat this issue, IPv6 uses 128 bit addresses, allowing 3.4 x 1038 unique IP addresses. This is equal to 340 trillion trillion trillion IP addresses. IPv6 is written in hexadecimal notation, separated into 8 groups of 16 bits by the colons, thus (8 x 16 = 128) bits in total. Which essentially means both me and you wont see IPv6 run out in our life times nor will you kids kids.
Answer:
An Array
Explanation:
Array and Object is a good use for storing data and accessing it
"Comparing the cost of care provided to Medicare beneficiaries assigned to primary care nurse practitioners and physicians" is a study that
<h3>What is the cost of Medicare according to the above study?</h3>
The study shows that after controlling for demographics, geography, comorbidities, and proclivity to visit an NP, Medicare evaluation and management payments for patients allocated to an NP were $207, or 29%, less than PCMD assigned beneficiaries.
The similar tendency was seen for inpatient and total office visit payment amounts, with NP-assigned beneficiaries receiving 11 and 18 percent less, respectively. The work component of relative value units yields similar results.
Learn more about Medicare:
brainly.com/question/1960701
#SPJ4