1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Nataliya [291]
3 years ago
5

I need help with this question make sure to answer where the point is supposed to be at.

Mathematics
2 answers:
agasfer [191]3 years ago
5 0

Answer:

for the 1 and 5/6, place it at the line before 2 and for 2 and 1/3, place it at the 2nd line past 2

qaws [65]3 years ago
5 0

Answer:

Step-by-step explanation:

You might be interested in
A new curved screen TV costs $3,508.80. A family makes a down payment of $450 and pays off the balance in 24 equal monthly payme
77julia77 [94]

Answer:

$127.45

Step-by-step explanation:

First, subtract 450 from 3,508.80:

3,508.80 - 450 = 3058.8

Then, divide this by 24 to find the monthly payment:

3058.8/24

= 127.45

So, the monthly payment was $127.45

5 0
3 years ago
Daisy measured the heights of 20 plants.
sergiy2304 [10]

Answer:

  • 30.5 cm

Step-by-step explanation:

<em>Refer to attached</em>

  • Height of plants (h) >> Frequency >> Midpoint >> Frequency x midpoint
  • 0 <h < 10 >>  1  >> 5 >> 5
  • 10 <h < 20 >> 4 >> 15 >>  60
  • 20 <h < 30 >> 7 >> 25 >> 175
  • 30 <h < 40 >> 2 >> 35 >> 70
  • 40 <h < 50 >> 3 >> 45 >> 135
  • 50 <h < 60 >> 3 >> 55 >> 165

Sum of frequencies = 20

Sum of frequency x midpoint product = 610

<u>Mean height </u>

  • 610/20 = 30.5 cm

5 0
4 years ago
It takes 15 electricians 24 days to wire a new housing subdivision. how many days would 18 electricians require to do the same j
Romashka [77]
15 electricians worked for 24 days to the whole job, now, there are 15 of them, so on any given day, each electrician worked one whole day, in 24 days, that one electrician worked 24 days total.

now, there were 15 electricians on any given day though, since each one of them worked the whole day that one day, so the "days work worth" on a day is 15, so the house gets 15days worth of work because of that.

so how many "days worth" did all 15 do on the 24 days, well, 15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15, namely 15 * 24, or 360 days worth of work.

since it takes 360 days worth of work to do the whole wiring, in how many days would 18 electricians do it?   360/18.
4 0
4 years ago
Read 2 more answers
Peter and Henry went to the movies Peter bought the two Movie tickets for 7 dollars each. How much did he spend for the movie ti
statuscvo [17]
$14

7•2=14
Peter bought both tickets and the each cost $7 so 7 times 2 would be 14
3 0
2 years ago
Read 2 more answers
Which unit rate is the lowest price per ounce? (5 points) Choice A: 5 ounces of raisins for $1.49 Choice B: 12 ounces of raisins
bija089 [108]
1.49/6 = 0.248 per oz
3.59/13 = 0.276 per oz

lowest price is A. 6 oz for 1.49
3 0
4 years ago
Read 2 more answers
Other questions:
  • Find the zeros of the polynomial function. f(x) = x2 + 12x + 20
    9·2 answers
  • 1) 4x - 3y=3<br>x+3y= 12​
    9·2 answers
  • I really need help on where to put them fast!
    8·1 answer
  • Help pleasee!! this is due tomrw I need answers asap!!
    13·1 answer
  • What is the equation of a line that passes through the point -(6,6) and has a slope of 1/3​
    14·1 answer
  • Helppppppppppppppppppppp
    12·1 answer
  • 1
    10·1 answer
  • Two figures are shown below.
    6·1 answer
  • I need help!!!! find x and y please
    8·1 answer
  • Please help. Don’t answer if you don’t know the answer. Your waisting my points and answer spaces when you do so. Thanks-
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!