7

6. On 3/1/19, Kepple Inc. borrowed funds on a 12%, two-year note, to finance the construction of a new warehouse which qualifies

for interest capitalization. Construction on the project began on 4/1/19 and was completed on 11/1/19. Kepple has a calendar year-end. Rounded to the nearest whole month, over how many total months in 2019 should interest be capitalized under the current interest capitalization rules?
Business
1 answer:
Tcecarenko [31]3 years ago
3 0

Answer:

The interest would be capitalized for 7 months time and must be calculated at 12% of the actual amount used for the construction of the new warehouse.    

Explanation:

The interest can only be capitalized for the period the loan amount was used to make the asset ready for use. Also note that the part of loan amount used will only be used to calculate the interest which would be capitalized which means if the company borrowed $1.2 million at 12% and used only $0.6 million of the total loan for construction of the building then the amount used will be $0.6 to compute the interest that will be capitalized.

The time period will be the corresponding time of commencement of construction and amount borrowed to the date the construction of the asset has been completed. So here, the time period for which the interest would be capitalized would be for 7 months (4/1/19 - 11/1/19) because the construction was completed within 7 months.

You might be interested in
When one party takes specific action to cover a material fact from another party, fraud by enticement occurs. question 1 options
Vladimir79 [104]
The answer to the question above is FALSE. It is not Fraud by Enticement but rather, Fraud by Concealment. This happens when one party takes a certain action to hide or conceal a material fact from another party. For example, when one company decides to purchase a material from the other and that the first company decides not to show all of the details of the product, which would then later on discovered that it is not brand new or have been repaired several times, they can sued for fraud by concealment.
8 0
3 years ago
Bitcoin is worth it?
stellarik [79]
You can easily trade bitcoin for cash or assets like gold instantly with incredibly low fees. The high liquidity associated with bitcoin makes it a great investment vessel if you're looking for short-term profit. Digital currencies may also be a long-term investment due to their high market demand.
7 0
2 years ago
Regan owns and manages The Coffee Shoppe. She likes to experiment with different management styles and life philosophies. She re
Art [367]

Answer:

its cold outside thats the answer

Explanation:

5 0
3 years ago
At the beginning of June, Kimber Toy Company budgeted 23,000 toy action figures to be manufactured in June at standard direct ma
arsen [322]

Answer:

Direct Material quantity variances = $600 (Favorable)

Direct labor time variances = $279 (Unfavorable)

Explanation:

Requirement A,

We know,

Direct Material quantity variances = (Actual quantity - Standard quantity) × Standard cost per unit

Given,

<em>a) Standard cost per unit = $0.50 per pound</em>

b) Actual Quantity = Actual direct materials ÷ Standard cost per unit

Actual Quantity = $21,100 ÷ $0.50

<em>Actual Quantity = 42,200 pounds.</em>

c) Standard quantity = Actual production ÷ Standard cost per unit = 20,500 toys ÷ $0.50 per pound

<em>Standard quantity = 41,000 pounds</em>

Putting the values into the above formula,

Direct Material quantity variances = (41,000 - 42,200) pounds × $0.50 per pound

Direct Material quantity variances = $600 (Favorable)

As the standard quantity is higher than actual quantity, the company is in favorable condition.

Requirement B

We know,

Direct labor time variances = (Actual Hour - Standard Hour) × Standard labor rate per hour

Given,

<em>a) Standard labor rate per hour = $9.00</em>

b) Actual Hour = Actual direct labor ÷ standard direct labor rate

Actual Hour = $9,500 ÷ $9.00

<em>Actual Hour = 1,056 hours</em>

c) Standard hour = [(Standard Direct labor ÷ standard direct labor rate) ÷ Budgeted production] × Actual production

Standard hour = [($10,350 ÷ $9.00) ÷ 23,000] × 20,500

<em>Standard hour = 1,025 hours</em>

Putting the values into the above formula,

Direct labor time variances = (1,056 - 1,025) hours × $9.00

Direct labor time variances = $279 (Unfavorable)

As the standard hour is lower than actual hour, the company is in unfavorable condition.

3 0
3 years ago
What common business mistake can cost you everything​
Amiraneli [1.4K]
Advertisements, discount offer,sales,
5 0
3 years ago
Other questions:
  • Wizards are step-by-step guides for tasks in application software
    13·1 answer
  • Dan buys a property for $260,000. he is offered a 30-year loan by the bank, at an interest rate of 6% per year. what is the annu
    12·1 answer
  • The following selected transactions relate to cash collections for a firm that uses a cash register. Present entries to record t
    5·1 answer
  • The advantage of setting priorities in your life is that you can _________. a. Easily change your habits and behaviors overnight
    7·2 answers
  • A project will produce cash inflows of $1,750 a year for four years. The project initially costs $10,600 to get started. In year
    14·1 answer
  • Two years ago, the de Castellane Manufacturing Company included its employees in a profitsharing plan in which workers receive s
    9·1 answer
  • . What is unethical behavior?
    13·2 answers
  • The marginal rate of transformation of x for y represents:__________
    13·1 answer
  • Assume that beer is an inferior good. If the price of beer​ falls, then the substitution effect results in the person buying​ __
    8·1 answer
  • Trey Morgan is an employee who is paid monthly. For the month of January of the current year, he earned a total of $4,540. The F
    9·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!