The correct answer would be 81
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Hey im trying to answer it, it keeps saying im adding a link or bad words. Im new here so im not sure what to do about that. Did you maybe do something to cause that?
Answer:
B) must be balanced by a statement that trading options can also result in significant losses.
Explanation:
Representatives do not trade securities by themselves, they only enter orders on behalf of their clients and following their clients' orders. That means that the clients assume the risk of losing money due to a bad investment. The clients are also the ones that benefit the most since it is their money being invested. Any statement that states the possibility of significant earnings, must also include the possibility of significant losses.
I think Jennifer’s payment for the month is 3,800