The government must control the money supply.
Answer:
Project Size IRR
A $650,000 14.0%
B 1,050,000 13.5
C 1,000,000 11.2
D 1,200,000 11.0
Explanation:
Based on the information given the set of projects that should be accepted should be the project that has higher Internal rate of return (IRR) than the Weighted average cost of capital (WACC) percentage of 10.8% . Hence, the set of projects that should be accepted are: Project A,B,C,D
Project Size IRR
A $650,000 14.0%
B 1,050,000 13.5
C 1,000,000 11.2
D 1,200,000 11.0
Total $3,900,000
Based on the above we can see that Project A,B,C,D has a total of $3,900,000 which is higher than the retained earnings amount of $2,500,000.
Therefore the set of projects that should be accepted should be Project A,B,C,D
Answer:
The balance in the accumulated depreciation account at the end of the second year is $146,000.
Explanation:
Straight line method charges a <u>fixed depreciation charge</u> on the asset during its period of use.
Depreciation Expense (Straight line) = Cost - Residual Amount ÷ Estimated Useful life
= $778,000 - $48,000 ÷ 10
= $73,000
Therefore, for each year, a depreciation expense of $73,000 is charged to profit an loss.
Accumulated Depreciation Calculation :
Depreciation Expense : Year 1 $73,000
Depreciation Expense : Year 2 $73,000
Total Expense $146,000
Answer:
Instructions are listed below
Explanation:
Giving the following information:
For the purchase option:
Buying price= $22 per unit.
For the make option:
Weekly rental payment of $30,800
The firm also has to hire five operators to help make product A. Each operator works eight hours per day, five days per week at the rate of $14 per hour.
The material cost for the make option is $15 per unit of product A.
A) We need to find the number of units that makes the unitary fixed costs= $7
Weekly rental= 30800
Direct labor= ($14*8 hours*5workes)*5 days= 2800
Total fixed costs= $33,600
Unitary fixed costs= total fixed costs/ Q
7=33600/Q
Q= 4800 units
B) Now Q= 6600
Buy= 6600*22= $145,200
Make= 6600*15 + 33600= $132,600
Answer: $3,564.50
Explanation:
The total amount that the company will pay for the merchandise is the net cost of the merchandise, less a 3% cash discount, plus the transportation costs. The cash discount normally only applies to the merchandise and not the transportation costs.
The cost of the merchandise is $3,600 less the $250 refund, which equals $3,350. With a 3% cash discount they will pay 97% of this amount, which is $3,249.50. After adding the additional transportation charge of $315, the total amount to be paid is $3,564.50.