Answer:
(1, -7)
Step-by-step explanation:
P(3,4)
3 up ---> y = 4 + 3 = 7
2 left ----> x = 3 - 2 = 1
new point (1, 7)
after 180 rotation around origin
point is (-1, -7)
now reflection over y-axis
(1, -7)
900,000,000. move the decimal until you have a number between 1-10 so move it 8 times and you'll have 9×10^8
Answer: 0.10
Step-by-step explanation:
Find the number in the hundredth place
9
9
and look one place to the right for the rounding digit
9
9
. Round up if this number is greater than or equal to
5
5
and round down if it is less than
5
5
.
0.10
Answer:
38
Step-by-step explanation:
APEX
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15