Answer:
Debit to cost of goods sold and credit to factory overhead
Explanation:
Here we are interested in knowing the appropriate journal entry when the factory overhead is under applied.
What happens to the factory overhead journal in this case is that the we should have an adjusting journal entry.
The adjusting journal entry here is that we debit cost of goods sold and credit factory overhead
Answer: b. Its quick ratio decreases.
Explanation:
The Quick ratio is calculated net of inventory to determine if a company can cover its current liabilities with its more liquid current assets. The formula is to subtract Inventory from the Current Assets and then divided that by the Currency liabilities.
The Quick ratio will be less than before because the number of current assets will not change but the amount of current liabilities will change as the goods were purchased on credit. With a larger denominator, the resultant ratio will be less than before.
Answer:
Cash 2,157 debit
bank service expense 85 debit
account receivables 2,242 credit
Explanation:
To record the bank memorand:
The collection in behalf of the firm will increase cash
The new print the checks will be considered either miscellaneuos expense or bank service expense either way, will decrease cash.
Net cash variation: 2,242 - 85 = 2,157
For the Company errors another entry will be made looking for errors between our numebrs and the bank.
Answer:
Jake Werkheiser will have $170,322.48 at the end of 12 years.
Explanation:
We use the following formula to find the future value,
S= future value
R= yearly payment =$5000
i= rate of interest = 9%=0.09
n =time =12 years.
Now putting the value of i, n, R
=$170,322.48
Jake Werkheiser will have $170,322.48 at the end of 12 years.
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186