Answer:
a) $28 Million
b) -$24 Million
Explanation:
The first part of the question is to determine the pension liability tht should be reported in the balance sheet
To do this, we use the following formula
Projected Benefit Obligation - The Plan Assets
= $65 million - $37 Million = $28 Million
Part B) This part says to dettermine the amount JDS would report if the planned asset increase to $89 million
The formula Projected Benefit Obligation - The Plan Assets still should be used but there is a difference as follows
$65 million - $89 Million = -$24 Million
Answer:
New wants continue to develop and willingness to meet them is limited.
Explanation:
Scarcity arises because of -'Unlimited Wants', but 'Limited Resources' having 'Alternative Uses'.
Wants are different from needs: needs are basic but wants are not basic - eg food is need but pizza is want. So, the basic essence of wants is that they are ever increasing. Contrasting to these never ending wants, resources are unlimited & have alternative uses. Eg- Land may be used to create industries or houses, it is limited in contrast to its unlimited want.
The correct answer would be B. Depreciation
Answer:
Dr land $278,000
Dr building $347,500
Dr equipment $556,000
Dr inventories $208,500
Cr cash $1,390,000
Explanation:
The total amount spent in acquiring the assets is $1,390,000 which needs to be shared between the assets acquired on the basis of individual values of the assets
Total of individual assets' values=$304000+$380000+ $608000+$228000=$ 1,520,000.00
Cost attributable to land:$304000/$1520000*$1,390,000=$ 278,000.00
Cost attributable to Building:$380000/$1520000*$1390000=$ 347,500.00
cost attributable to equipment=$608000/$1520000*$1390000=$556,000.00
cost attributable to inventories=$228000/$1520000*$1390000
=$208,500.00
Answer:
Answer:
1. MCE = 21.42%
2. Delivery Cycle Time 22 days
Explanation:
The Manufacturing Cycle Time is given by the formula:
Manufacturing cycle time = Inspection Time + Process Time + Move Time + Queue time
Here we have
Inspection time =1.5 days
Processing time =3.0 days
Move time =2.5 days
Queue time= 7.0 days
Wait time= 8.0 days
Manufacturing Cycle Time = 1.5+3.0+2.5+ 7.0= 14.0 days
MCE= Manufacturing Cycle Efficiency Time= Process Time/ Processing Time + Inspection Time + Move Time + Queue time
MCE = 3/ 14=0.2142= 21.42%
It means that MCE consists of 21.42 %actual processing and 79 % consists of non value added activities.
2. Delivery Cycle Time= Manufacturing Cycle Time + Wait time
Delivery Cycle Time= 14.0 days + 8.0 days= 22.0 days
The difference between wait time and queue time is that wait time is the time when the customer places an order until it is delivered.And queue time from the start of the production of the order.