Answer:
A. See attached image
B. $93,446.35
C. He should accept the first offer from the hardware chain
Explanation:
A time line is a line that chronological orders events according to the time they occurred
The present value is the present value of after tax cash flows from an investment.
The present value can be calculated using a financial calculator.
Cash flow for year 1 =$28,000
Cash flow for year 2 =$21,000
Cash flow for year 3 -9 =$12,000
Cash flow for year 10 =$15.000
I = 11%
PV =$93,446.35
Hart should accept the first offer from the hardware chain because the present value of the first offer $93,446.35 is greater than the present value of $90,000.
I hope my answer helps you.
Answer:
a. $22,500
Explanation:
The computation of the depreciation expense using the straight line method is shown below:
= (Original cost - salvage value) ÷ (useful life)
= ($750,000 - $75,000) ÷ (10 years)
= ($675,000) ÷ (10 years)
= $67,500
In this method, the depreciation is same for all the rest of the useful life
Now for 4 months, it would be
= $67,500 × 4 months ÷ 12 months
= $22,500
The four months is calculated from January 1 to May 1
Answer :
True required initial investment = $26,954,178
Explanation :
As per the data given in the question, we need to do following calculations
Weighted average flotation cost = ( % flotation cost of debt × weight of debt) + (% flotation cost of preferred equity × weight of preferred equity) + (% flotation cost of common equity × weight of common equity)
= (3% × 35%) + (7% × 10%) + (10% × 55%)
= 0.0725
=7.25%
It means out of total capital which is raised 7.25%, would be the flotation cost.
Let total capital raised be X
So X × (1 - 7.25%) = $25 million
X = $25 million ÷ (1- 7.25%)
X = $26,954,178
Answer:
B. A violation of establishment of responsibility
Explanation:
They both should have established something different to work on but for both of them to work the same cash register, it is a violation of establishment of responsibility
Answer:
Explained
Explanation:
Change control process has a purpose to ensure that the changes are made within a project in a consisted manner and the appropriate stake holders are informed about the state of the product, changes to it and the cost and the schedule impact of these changes. The change control board in a software company often consists of the development manager, the test lead and the product manager( Subject matter expert).