Answer:
The correct answer is C.
Explanation:
Giving the following information:
They generally use a static budget with the following costs based on 8,000 units per month: Indirect materials, $22,000; indirect labor, $25,000; utilities, $12,000; supervision, $4,000; depreciation, $18,000.
Unitary variable costs= (22,000 + 25,000 + 12,000)/8,000= 59,000/8,000= 7.375
Units= 9,000
Total variable cost= 9,000*7.375= 66,375