Answer:
<u> The total amount of direct materials $ 1233</u>
<u>The total amount of direct labor $ 315</u>
<u>The total amount of manufacturing overhead $ 322</u>
<u>Profit for 1 recliner= $ 2480/6= $ 413.33</u>
Explanation:
Tandoi Furniture
Direct Materials for Job 310:
Lumber: 50 units at $5 per unit $ 250
Padding: 11 yards at $13 per yard $ 143
Upholstery fabric: 28 yards at $30 per yard $ 840
<u> The total amount of direct materials $ 1233</u>
Labor Time Records for Job 310:
Jeff Paradise: 11 hours at $9 per hour $ 99
John Maddock: 12 hours at $18 per hour $ 216
<u>The total amount of direct labor $ 315</u>
Tandoi Job 310's Manufacturing Overhead
Manufacturing overhead ($14 *23 hours) $ 322
<u>The total amount of manufacturing overhead $ 322</u>
2. Total Maufacturing Costs for Job 310= $ 1233+ $ 315 + $322= $ 1870
Sale Price of 6 recliners= 6 * $ 725= $ 4350
Profit Job 310= $ 4350- $ 1870= $ 2480
<u>Profit for 1 recliner= $ 2480/6= $ 413.33</u>