45= 100%
72= ?%
100×72/45 = 160
B can finish the job alone in 24 days.
In work-rate problems, a certain person can complete a fraction of the job for a specific timeframe. As stated in the problem, A and B can finish the job by working together for 8 days. It must be noted that the fraction of the job they can finish individually per day is additive.

A can complete the work in 12 days and finish 1/12 fraction of a job per day. This can be substituted directly to the equation to solve for the time B needed to finish the work.



This means that B can do 1/24 fraction of the job per day and can completely finish the job in 24 days.
For more rate work-rate problems, please refer to the link brainly.com/question/14464103.