Answer:
$714,980.95
Explanation:
The most it would be willing to pay is the present value of the cash flows
present value is the sum of discounted cash flows from a project
present value can be determined with a financial calculator
Cash flow each year from year 1 to 6 = $150,000
I = 7%
Present value = $714,980.95
To find the PV using a financial calculator:
1. Input the cash flow values by pressing the CF button. After inputting the value, press enter and the arrow facing a downward direction.
2. after inputting all the cash flows, press the NPV button, input the value for I, press enter and the arrow facing a downward direction.
3. Press compute
i literally love this question so much. i'm not sure if this is fr, but probably a guy best friend or smth. if you need help i'm here for it. i'm a girl so i'm pretty sure that means i know girls better than any guy. i'm happy to help you out with any troubles! cheers.
Answer:
Cost of equity is 11.2%
WACC is 8.74%
Explanation:
The formula for cost of equity is given below:
Cost of equity=risk free rate+(Beta *risk premium)
risk free rate is the treasury bill rate of 4%
Beta is 0.9
market risk premium is 8%
cost of equity=4%+(0.9*8%)=11.2%
WACC=Ke*E/V+Kd*D/V*(1-t)
Ke is the cost of equity of 11.2%
Kd is the cost of debt of 5%
t is the tax rate of 40% or 0.4
E is the equity weighting of 70% or 0.7
D is the debt weighting of 30% or 0.3
V is the E+D=0.7+0.3=1
WACC=11.20%
*0.7/1+(5%*0.3/1*(1-0.4)
WACC=7.84%
+0.90%
=8.74%
You’re answer would be D love!
Answer:
True
Explanation:
A cost sheet is a statement that contains all the cost incurred on a cost unit or a cost centre. A typical cost sheet will accumulate all the direct and indirect material consumed in the production of a product. Also included in the cost sheet is direct labor incurred in the making of a product including allocated overhead. With this, the margin on a product can be observed from a cost sheet.