As charging technology currently has a huge influence on how effortlessly and conveniently drivers can charge their electric vehicles as part of their daily routine, Continental is presenting global innovations for this area of electromobility for the first time.
Answer:
d. $5,000
Explanation:
Patnode's information is missing, so I looked it up. I found the balance sheet for 2014 and 2015. Hope that it is the same question:
total depreciation expense for 2015 = change in accumulated depreciation (2015 - 2014) + change in accumulated amortization (2015 - 2014) = ($3,000 - $0) + ($3,000 - $1,000) = $3,000 + $2,000 = $5,000
Answer: work hard; $65; less; $85
Explanation:
The following can be deduced from the question:
The Expected profit from working hard will be:
= (90% × $200) + (10% × $50)
= (0.9 × $200) + (0.1 × $50)
= $180 + $5
= $185
Then, the profit will be the difference between revenue and coat which will be:
= $185 - $100
= $85
Then, the expected profit from shirking will be:
= (90% × $50) + (10% × $200)
= (0.90 × $50) + (0.10 × $200)
= $45 + $20
= $65
Then, the profit will be:
= $65 - $0
= $65
Eric will (work hard) because the net gain of ($65) from shirking is (less) than the net gain of ($85) from working hard.
Answer: hello your question is incomplete attached below is the complete question.
answer :
3.02 million, 2.96 million, 2.91 million
Explanation:
<u>Determine the swap rate over a 3-year period</u>
swap rate = forward exchange rate * exchange amount
For year 1
1.4 * ( 1 + 0.03 / 1 + 0.05 ) * 2.2 million
= 1.4 ( 0.98095 ) * 2.2
= 3.02 million
For year 2
1.4 * ( 1 + 0.03 / 1 + 0.05 )^2 * 2..2 million
= 1.4 ( 0.98095 )^2 * 2.2 million
= 2.96378 million
For year 3
1.4 * ( 1 + 0.03 / 1 + 0.05 )^3 * 2.2 million
= 1.4 ( 0.98095 )^3 * 2.2 million
= 2.90733 million
Answer:
The correct answer is letter "A": can be used to estimate the projected cost of completing the project.
Explanation:
The Cost Performance Index or CPI measures the projected cost of work completed compared to the current cost spent. The CPI represents a ratio of earned value to actual cost. If the CPI is greater than one, the project is under budget. When the CPI equals one the planned and actual costs are equal. If the CPI is higher than one, the project is over budget.