Answer:
option 2) smaller
As CE is the amount which if the agent gets with certainty, then agent will be indifferent between playing lottery or getting that amount with certainty
So L2 is more risky, & agent is risk averse, so agent will be ready to accept a lower amount with certainty ( as compared to the amount for a safer option : L1)
So CE of L2 will be lower
The correct answer is C,
A good is said to have an inelastic supply if the suppliers did not have any choice than producing it even though the cost of production is high and the buyers did not have any choice than buying it even though it is expensive.
No one can do without shoes, even if they are expensive, we still need to buy them.
Answer:
False
Explanation:
As a company's sales level increases, its current assets will increase, e.g. cash, inventories, accounts receivables increase. generally, also the fixed assets increase, specially if the firm was previous producing at full capacity even before total sales increased. But as sales increase, not only do the company's assets increase, its current liabilities generally increase also, and its profits should increase. In this case, 60% of the company's profits are reinvested in the company, and the liabilities represent more than half of the total assets. Therefore, it is possible that the company needs external financing, but it is also possible that it doesn't. You cannot assume that the company will necessarily need external financing, because retained earnings and the increase in current liabilities might be enough to finance the company's growth in sales.
Answer:
Over/under allocation= $30,000 overapplied
Explanation:
Giving the following information:
Manufacturing overhead applied $150,000
The actual amount of manufacturing overhead costs 120,000
To calculate the ending balance, we need to determine whether the overhead was under or over applied:
Over/under allocation= real MOH - allocated MOH
Over/under allocation= 120,000 - 150,000= 30,000 overapplied
As far as I remember, at the end of the systems implementation phase, the final report to management should include these elements:
1. <span>a comparison of actual costs and schedules to the original estimates;
2. </span>final versions of all system documentation;
3. <span>planned modifications and enhancements to the system that have been identified;
It's necessary thing in system analysis.</span>