Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,
We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:
P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,
0.726 is the probability that the project will be completed in 33 days or less.
Answer:
(x)=+1
Step-by-step explanation:
C) closest to 2/5.
2/3 is bigger than half 2/10 would be like less than 1/4
Answer:
-4y + 20
Step-by-step explanation:
4(-y+5)
What we need to do here is get rid of the parentheses, which can be achieved through multiplication.
This is another way of saying 4 times -y plus 4 times 5.
Let's break the the parentheses down into 2 separate formulas.
4(-y) and 4(5)
Now we can multiply these two together to get -4y and +20. When combined, we get -4y +20.
Answer:
They both have no possible solution.
Step-by-step explanation:
Don't know how to explain, but it's 100% right