The decision to build the park or not would be based solely
on the cost – benefit relationship of this project. Since there is no other
factor considered in this problem, you only need to see if the benefit of
constructing the park would exceed its cost. In this problem, the cost to
construct the park is $20,000 while the marginal benefit would be $24,000
($8,000 x 3 families that can benefit from this project). Therefore, you can
say that the benefit has exceeded its cost. As a conclusion, the neighborhood
park should be built because it benefits the families living in that area more
than its cost.
Answer:
Direct material price variance= $12,500 unfavorable
Explanation:
Giving the following formula:
The standard price per pound is $2.00.
The actual quantity of materials purchased and used in production is 50,000 pounds.
The actual purchase price per pound of materials was $2.25.
<u>To calculate the direct material price (spending) variance, we need to use the following formula:</u>
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (2 - 2.25)*50,000
Direct material price variance= $12,500 unfavorable
Answer:
Charges current production cost directly to work-in-process inventory
Explanation:
The blackflush costing is the costing method in which the present cost of production would be charged to the work in process inventory in a direct way
Therefore as per the given situation the second option is correct
ANd, the rest of the options are wrong as it does not meet the criteria
So the second option would be taken into consideration
Instructional<span> coordinators </span>can provide<span> training for </span>teachers<span> in curriculum</span>
Mike brought 100 shares costing $53 each.
Total costs of shares= 100*53
=$5300
He got dividends of $1.45 per share. A dividend is money that is earnt back from a share.
Total dividend amount = 1.45*100
=$145
I'm assuming that Mike sold his shares at the end of the year. He sells for $60 each.
Total sales amount=60*100
=$6000
The rate of return in this instance can be defined as the amount of money made back from a share.
Rate of return= total earnings/ costs
Total costs= $5300
Total earnings=$6145
6145/5300=1.1594
=15.9%
Hope this helps! :)