Answer:
Explanation:
The original Xbox: November 15, 2001
The original PS1: December 1, 1994
Xbox 360: November 22, 2005
Ps2: March 4, 2000
Ps3: November 11, 2006
Xbox One: November 22, 2013
Ps4: November 15, 2013
Nintendo Ds: November 21, 2004
Nintendo 3ds: February 26, 2011
Gameboy: April 21, 1989
Nintendo Switch: March 3, 2017
<span>Before GUIs became popular, the command line interface (CLI) was the most commonly used.
</span>GUI stands for Graphical User Interface . Like its name says it is a graphical interface <span>that allows interaction with users through graphical icons and visual indicators , rather than through text-based interface.</span><span>
Command line interace (CLI) is text-based interface in which </span>the user <span>issues commands to the program in the form of successive lines of text.</span>
Answer:
Network mapping.
Explanation:
Network mapping seems to be the method of mapping the server visibly and rationally in order to determine the relations at mid of the network as well as the not same nodes.
- Network mapping is the practice of security checking using software to search against services running on networks.
- Network performance applications and software contains certain network mapping functions that customize the network
Answer:
#include <iostream>
#include <cstdlib>
using namespace std;
int main() {
int[] array = new int[10];
int index = 0;
while(index < array.size()){
int number = (rand() % 100) + 1;
for (int i = 0; i < 1; i++) {
array[index] = number;
cout<< "Position "<< index << "of the array = "<< number << endl;
++index;
}
}
}
Explanation:
The while loop in the source code loops over a set of code ten times, The for loop only loops once to add the generated random number between 1 and 100 to the array of size 10. At the end of the for loop, the index location and the item of the array is printed out on the screen. The random number is generated from the 'rand()' function of the C++ standard library.
Answer:
Optimistic duration
Explanation:
The following three concepts are Project management concepts:
Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.
Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc
Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.
Which of the following is the estimate of the minimum amount of time it would take to perform a task?
The answer is Optimistic duration