Answer and Explanation:
The journal entry to record the issuance of the bond is as follows:
Cash Dr (5,000 × 103) $515,000
Discount on bond payable Dr $4,485,000
To Bond payable (5,000 × $1,000) $5,000,000
(Being the issuance of the bond is recorded)
Here cash and discount on bond payable is debited and credited the bond payable
Answer:
Explicit costs are the costs which requires the money to pay.
On the other hand, implicit costs refers to the benefit that is foregone by choosing some other work or doing some other activity.
Therefore,
Explicit costs are as follows:
1. Wages pays to his hired hand
2. Buys feed for his cows.
3. Gas expense that is used in truck
Implicit costs are as follows:
1. Foregone income of $27,000 from working at a dairy plant as a technician.
2. Time taken for extracting milk from all the cows.
Answer:
$55,300
Explanation:
Calculation to determine what The net income for December would be:
NET INCOME FOR DECEMBER
Revenue $327,000
Less cost of goods sold ($228,900)
(70%*$327,000)
Gross profit $98,100
($327,000-$228,900)
Less Depreciation ($17,400)
Less Operating expenses ($25,400)
Net Income $55,300
Therefore The net income for December would be:55,300
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.