Answer:
The correct answer is d) Increase the proportion of executive compensation that comes from stock options and reduce the proportion that is paid as cash salaries.
Explanation:
Option D. represents two situations that perfectly describe the interest that the shareholders pursue: the maximization of the profits of the company where they have their resources invested.
The shareholder, on the other hand, is also an investor, since he contributes capital with a view to obtaining a dividend.
Its investment is said to be in equities, given that there is no contract through which the shareholder will receive fixed fees in return for his investment. Their remuneration is through two ways:
- Dividend
- Increase in the price of the company. This is produced by its good progress and its ability to generate future benefits, as well as by the increase in assets through past benefits.
Answer:
$1905
Explanation:
Here we will have to calculate Economic Order Quantity to lower the ordering ordering and holding cost as much as we can. So here we will use the following formula to calculate the best number of units that we should order, which is as under:
Economic Order Quantity = SquareRoot (2 * Annual Demand * ordering cost per order / Holding cost per unit per year)
Here
Annual Demand = 900kg of palm oil per day * 52 weeks * 5 day a week / 7
Annual Demand = 900 * 52 * 5 / 7 = 33,429
And
Ordering cost per order = $57 per order
Annual holding cost per unit per year is 20% of $5.25 per kg which is $1.05.
So by putting values, we have:
Economic Order Quantity = Square Root (2 * 33,429 * 57 / 1.05)
Economic Order Quantity = 1905 kgs
Answer:
Answer:
1. MCE = 21.42%
2. Delivery Cycle Time 22 days
Explanation:
The Manufacturing Cycle Time is given by the formula:
Manufacturing cycle time = Inspection Time + Process Time + Move Time + Queue time
Here we have
Inspection time =1.5 days
Processing time =3.0 days
Move time =2.5 days
Queue time= 7.0 days
Wait time= 8.0 days
Manufacturing Cycle Time = 1.5+3.0+2.5+ 7.0= 14.0 days
MCE= Manufacturing Cycle Efficiency Time= Process Time/ Processing Time + Inspection Time + Move Time + Queue time
MCE = 3/ 14=0.2142= 21.42%
It means that MCE consists of 21.42 %actual processing and 79 % consists of non value added activities.
2. Delivery Cycle Time= Manufacturing Cycle Time + Wait time
Delivery Cycle Time= 14.0 days + 8.0 days= 22.0 days
The difference between wait time and queue time is that wait time is the time when the customer places an order until it is delivered.And queue time from the start of the production of the order.
Answer:
b) Larceny at the point of sale
Explanation:
Larceny at the point of sale -
It is a type of fraud , where the employee itself steal money from the employer during the point in the business , when is the sale is been made .
This type of fraud is very commonly seen in the retail business .
Same case is shown in the question data , where Jan Ashley , who works for the R & S departmental store , tries to steal money during the sale .
Answer:
The correct answer is $800 loss.
Explanation:
According to the scenario, the given data are as follows:
Purchased Amount = $18,000
Accumulated depreciation = $17,200
So, we can calculate the book value by using following formula:
Book value = Purchased Amount - Accumulated depreciation
By putting the value in the formula, we get
$18,000 - $17,200 = $800
So, if company discarded the computer system, Then
Book value of computer system = Loss to the company
Hence, Company Loss = $800