Answer:
The correct answer is schedule (time), budget (cost) and performance (resources).
Explanation:
To develop the Schedule, the outputs of the processes will be used together with the determined planning tool:
- Plan the Schedule Management. It consists of establishing the necessary policies, procedures and documentation. In order to plan, develop, direct and control the Project Schedule.
- Define the Activities. It consists of identifying those activities necessary to carry out the Project successfully.
- Sequence the Activities. It consists of identifying and documenting what kind of dependency exists between the different activities.
- Estimate resources of the Activities. It consists in estimating what type and amount of resources we need and are available to execute each activity.
- Estimate the duration of the Activities. It consists of establishing approximately how much time is necessary to complete each activity. As well as the number of resources estimated in the previous process.
- Develop the schedule. It consists in analyzing and integrating the order of execution of activities, their duration, resource requirements and possible restrictions. All this, integrated into the planned planning tool, will generate the Project Schedule, and with it the Baseline of the Schedule.
- Check the schedule. It consists of following the status of the Project, monitoring its progress and comparing with the baseline to manage possible changes.
The work necessary to carry out the six processes of Time Management must be preceded by a planning effort by the Project team, which is part of the process Develop the Project Management Plan. From it we will obtain, among others, the Schedule Management Plan that determines a methodology, the planning tool used, the format and the criteria to develop and control the Project Schedule.
------
NOTE: If you need to extend the explanation given, you can make a comment or add a new question. I will be very pleased to help you.
Answer:
0.00914 ; 0.0062 ; 0.9847
Explanation:
Given the following :
Normal distribution :
Mean(m) = $4200
Standard deviation (sd) = 720
Amount VERY low = < 2500
Amount very high = > 6000
a. What percent of the days will the bank be notified because the amount dispensed is very low?
x < 2500
Finding the z-score :
Z = (x - mean) / standard deviation
Z = (2500 - 4200) / 720
Z = - 1700 / 720 = −2.361111
P(z < −2.361111)
Locating −2.361111 on the z- distribution table
-2.3 under 0.06 = 0.00914
P(z < −2.361111) = 0.00914
B) What percent of the time will the bank be notified because the amount is very high?
x > 6000
Finding the z-score :
Z = (x - mean) / standard deviation
Z = (6000 - 4200) / 720
Z = 1800 / 720 = 2.5
P(z > 2.5)
Locating 2.5 on the z- distribution table = 0.9938
P(z > 2.5) = 1 - 0.9938 = 0.0062
c. What percent of the time will the bank not be notified regarding the amount of funds being dispensed?
P(2500 < X < 6000)
P(2500 < X < 6000)
P(-2.36 < z < 0) + P(0 < z < 2.5)
= 0.4909 + 0.4938
= 0.9847
Weekly BC earnings of full time wage and salary workers by age race Hispanic or Latino ethnicity and sex
Answer:
Reagan’s claim that inflation rose sharply under Carter is supported by the data.
Explanation:
Correct on edg