Answer:
c) finish-to-start; start-to-start
Explanation:
Project dependencies are the time relationships between a predecessor and a successor in project management. In other words, these dependencies describe which activity among the two needs to start earlier or later and when it needs to start or finish compared to the other one.
The most common type of dependency in all projects (no matter the nature or industry) is the finish-to-start one, where the activity A needs to be completed before activity B starts, e.g. base nail polish has to be put before the top coat gets put on the nails.
The second most common type of dependency is the<em> start-to-star</em>t one, where two activities need to start at the same time. This is common for activities where synchronization is paramount.
Answer:
increased
Explanation:
Data provided in the question:
Price of a gallon of gasoline in 1972 = $0.35
CPI in 1972 = 0.418
Price of a gallon of gasoline in 2005 = $2.25
CPI in 2005 = 1.68
Now,
Real cost in 1972 = [ Nominal cost in 1972 ] ÷ [ CPI in 1972 ]
= $0.35 ÷ 0.418
= $0.837
Real cost in 2005 = [ Nominal cost in 2005 ] ÷ [ CPI in 2005 ]
= $2.25 ÷ 1.68
= $1.34
Hence,
The price of gallon of gasoline increased between 1972 and 2005