I<span>f Eva uses the earliest due date priority rule, the order of the dresses will be as follows: W (1 hour processing time, 1 hour due); Y (2 hrs processing time, 3 hrs due); V (3 hrs processing time, 5 hrs due); Z (5 hrs processing time, 7 hrs due); X (4 hrs processing time, 9 hrs due).</span>
It's easier to do the next step using real numbers. For example, if it's 11am now and W is due in 1 hour, then W is due at noon. If Y is due in 3 hours, then Y is due at 2pm, etc. Then, you need to use the processing time to see how long it will take to make the dresses. For example, since W takes one hour to process, it will be done by noon, its due date.
This means that W and Y will be altered on time, V will be 1 hour late, Z will be 4 hours late, and X will be 6 hours late. To find the average tardiness, add these extra hours (1+4+6) = 11, and divide by the total number of dresses (even the ones that weren't late) 5: 11/5 = 2.2 hours.
A business plan is a formal document that states the goals of the business as well as the intended process for reaching those goals. This provides a market analysis. This basically provides the investors an idea of how the company will make use of its money and conduct business.
f a $100 drop in the price of a $10,000 car resulted in an increase in the quantity of cars purchased from 100 to 110 and a $100 drop in the price of a $1,000 vacation rental resulted in an increase in the quantity of weekly vacation homes rented from 100 to 110, the price elasticity of demand the same for both the car and the vacation rental.
The elasticity remains unchanged because the percentage change in price and percentage change in quantity are tne same in both cases.