It should be under lined, when you press it it should have a different colour
Answer:
code reviewer
Explanation:
In this scenario, the project manager should advertise for a code reviewer. Usually a development team has at least 2 code reviewers that are very familiar with the code that is being written for the project. Once sections of code have been completed it is usually the case that both the project lead and a code reviewer both review the entire software to look for bugs and note improvements that can be made to make the code more efficient.
Answer:
The formula to enter in E14 is as follows:
=DAYS(D14,$E$10)
Explanation:
Required
Formula to calculate the number of days between E10 and D14
The syntax to do this is:
=DAYS(end_date,start_date)
So, we have:
=DAYS(D14,E10)
The question requires a mix of relative and mixed references because cell E10 will be constant in calculating the difference for dates in other cells.
In other words, the initial date is constant for all
So, the update formula is:
=DAYS(D14,$E$10)
Notice the $ between in E10; this represents mixed referencing
When dragged to E15 till E68, the formulas in the respective cells will be:
=DAYS(D15,$E$10) .............................. =DAYS(D68,$E$10)
Answer:Have a good dayyyyy
Explanation: can i be brainliest pls pls