The minimal completion time for the activities is the shortest possible time for all the activities to be finished. In doing this, we look at the path that would require the greatest amount of time. At the START node, we choose the path that would take the longest which is 7 days leading to ACTIVITY D. Next, we choose the path leading to ACTIVITY B which takes 5 days. Then, we move to ACTIVITY C taking 5 days and finally, reach the END which would take 6 days. So, the minimal completion time is:
7 + 5 + 5 + 6 = 23 days
Answer:
Option B
Step-by-step explanation:
Given:
As per the contract "Notification of the Buyer’s intent to do so must be made by written letter or phone call to the phone number and address listed below within one business week of delinquency.”
So,buyer needs to only notify the bank about the monthly payments in case of delinquency and not about if payment is going to be late or not.
Option B is correct
Notify the bank if a payment is going to be late !
Answer:
160
Step-by-step explanation:
n : d : s
8 : 12 : 20
davina = 48 sweets
48/12 = 4
8 + 12 + 20 = 40
40 x 4 = 160 sweets total